Advanced manual resource allocation
#1
Question 
Hi everyone,
I am trying to deal with manual function in advanced resource allocation.
I am dealing with a real scenario.
I need to declare an activity spanning from the beginning of march up to the end of may.
The total hours is 20.
Then I link myself as a resource to this task.
As soon as I save it, the planner spreads the effort during the first three days (8 hours each working day) using the flat function.
If I switch it to manual, I can declare a single hour each week (this activity is a training I will give to colleagues).
After that I apply it, the task in the gantt view is not editable anymore. Huh
If i switch the advanced allocation back to "flat" then the task goes to editable again.
Why?

I already have bought the Missing manual, but I really can't understand what's the use of the "manual" function indeed at this point.

Thank you.
Raffaele Pantaleoni